................of a subdivision: Episode 23:
We have had a rainy spring. Hard to put pipe in the ground when it is soaking wet. Having said that, progress is being made. The sanitary sewer main lines have been installed and we are about halfway through the installation of the storm sewer system. Nothing wrong here that a few dry weeks won't cure.
|
Preparing the ground for a storm structure |
|
Work completed about an hour ago |
|
Lifting the storm structure |
|
Attention to detail: cleaning mud off the bottom of the structure |
|
Put it right about there |
|
Right where it belongs |
|
D. R. Horton building out the 49 first phase lots |